February 2019

Stage 1

RMP & Associates undertake preliminary investigation and collate existing data and reports. 

March 2019

Stage 2

RMP & Associates develop report and concept plans on options for redevelopment. 
March 2019

Stage 3

RMP & Associates undertake market research. 
April 2019

Stage 4

RMP & Associates consult with Council on results of site and master planning considerations and develop a preferred option for the redevelopment of the site. 

May 2019

Stage 5

RMP & Associates report on results of site, plant and infrastructure assessment and provide cost estimates. 
June → July 2019

Stage 6

RMP & Associates present final report to Council.